ScheduledLink

class.NET 6 / 8 / 10.NET Framework 4.8Binarymission.WinForms.Controls.ProjectManagement

One link as the scheduler used it. Links that could not be honoured are not here; they are in ProjectSchedule.Problems instead.

public sealed class ScheduledLink

See also

Members at a glance

Properties
FromIdGets the id of the predecessor: the task that comes first.
IdGets the link's EffectiveId: its id, or from->to when it has none.
IsCriticalGets whether the link is part of the critical path.
LagGets the link's delay in working days; negative for a lead.
LinkGets the link this was checked from: the application's own object.
ToIdGets the id of the successor: the task that waits.
TypeGets which ends of the two tasks the link joins.

Properties

FromId

public string FromId

Gets the id of the predecessor: the task that comes first.

Id

public string Id

Gets the link's EffectiveId: its id, or from->to when it has none.

IsCritical

public bool IsCritical

Gets whether the link is part of the critical path.

Value
true when both its tasks are critical and this link is what holds the successor where it is, rather than some other link or date. The charts draw such links in their critical colour.

Lag

public int Lag

Gets the link's delay in working days; negative for a lead.

ToId

public string ToId

Gets the id of the successor: the task that waits.

Type

public TaskLinkType Type

Gets which ends of the two tasks the link joins.