WPF › Project Management › ScheduledLink
ScheduledLink
class.NET 6 / 8 / 10.NET Framework 4.8Binarymission.WPF.Controls.ProjectManagement
One link as the scheduler used it. Links that could not be honoured are not here; they are in
ProjectSchedule.Problems instead.
public sealed class ScheduledLink
See also
Members at a glance
| Properties | |
|---|---|
FromId | Gets the id of the predecessor: the task that comes first. |
Id | Gets the link's EffectiveId: its id, or from->to when it has
none. |
IsCritical | Gets whether the link is part of the critical path. |
Lag | Gets the link's delay in working days; negative for a lead. |
Link | Gets the link this was checked from: the application's own object. |
ToId | Gets the id of the successor: the task that waits. |
Type | Gets which ends of the two tasks the link joins. |
Properties
FromId
public string FromId
Gets the id of the predecessor: the task that comes first.
Id
public string Id
Gets the link's EffectiveId: its id, or from->to when it has
none.
IsCritical
public bool IsCritical
Gets whether the link is part of the critical path.
- Value
truewhen both its tasks are critical and this link is what holds the successor where it is, rather than some other link or date. The charts draw such links in their critical colour.
Lag
public int Lag
Gets the link's delay in working days; negative for a lead.
Link
public TaskLink Link
Gets the link this was checked from: the application's own object.
ToId
public string ToId
Gets the id of the successor: the task that waits.
Type
public TaskLinkType Type
Gets which ends of the two tasks the link joins.