ScheduleProblemKind

enum.NET 6 / 8 / 10.NET Framework 4.8Binarymission.WPF.Controls.ProjectManagement

What kind of problem the scheduler found in its input.

public enum ScheduleProblemKind

Members at a glance

ConstraintConflictA task that must start on a date is also held later by its links; the date is kept.
DuplicateLinkThe same link appears twice; the second is left out.
DuplicateTaskTwo tasks share an id; the first is used.
InvalidDateA date could not be read. Only text read by the charts can be invalid; it is ignored.
LinkCycleA link would make tasks wait for each other in a loop; it is left out.
LinkWithinSummaryA link joins a summary to one of its own subtasks; it is left out.
ParentCycleA task's parent chain leads back to itself; it is shown at the top level.
SelfLinkA link joins a task to itself; it is left out.
UnknownParentA task names a parent that is not in the plan; it is shown at the top level.
UnknownTaskA link names a task that is not in the plan; it is left out.
UnsupportedSummaryLinkA link leads into a summary by its finish, or out of one by its start, which a summary's rolled-up dates cannot honour; it is left out.

Members

ConstraintConflict

A task that must start on a date is also held later by its links; the date is kept.

DuplicateTask

Two tasks share an id; the first is used.

InvalidDate

A date could not be read. Only text read by the charts can be invalid; it is ignored.

LinkCycle

A link would make tasks wait for each other in a loop; it is left out.

LinkWithinSummary

A link joins a summary to one of its own subtasks; it is left out.

ParentCycle

A task's parent chain leads back to itself; it is shown at the top level.

UnknownParent

A task names a parent that is not in the plan; it is shown at the top level.

UnknownTask

A link names a task that is not in the plan; it is left out.