WPF › Project Management › TaskConstraintKind

TaskConstraintKind

enum.NET 6 / 8 / 10.NET Framework 4.8Binarymission.WPF.Controls.ProjectManagement

How a task's own planned date constrains it, beyond its links.

public enum TaskConstraintKind

Members at a glance

FinishNoEarlierThanThe task finishes no earlier than Finish.
MustStartOnThe task starts on Start even when its links would push it later. The conflict is reported in Problems.
StartNoEarlierThanThe task starts no earlier than Start, and later if its links require. This is what a planned start means when nothing else is said.

Members

FinishNoEarlierThan

The task finishes no earlier than Finish.

MustStartOn

The task starts on Start even when its links would push it later. The conflict is reported in Problems.

StartNoEarlierThan

The task starts no earlier than Start, and later if its links require. This is what a planned start means when nothing else is said.